Framework agreements explained
- Model rules
- UNCITRAL Model Law on Public Procurement 2011, article 32 and Chapter VII 1
- Types
- Closed and open framework agreements 1
- EU term limit
- Four years, longer only in exceptional cases duly justified 2
- Kenya term limit
- Three years, with at least seven alternative vendors, regulation 102(1) 3
- Tanzania
- Section 52, Public Procurement Act 2023 5
- Uganda
- Framework contracts, section 100 of the Act, Cap. 205 6
- World Bank
- Listed as a contract arrangement in paragraph 5.27, details in Annex VIII 10
What a framework agreement is
The UNCITRAL Model Law describes a framework agreement procedure as one run in two stages, with a first stage to select one or more suppliers or contractors to be parties to the agreement 1. In a closed framework agreement, no supplier that was not a party at the start can join later 1. An open framework agreement lets new suppliers be added 1. Where terms cannot be set with enough precision at the start, they are set or refined through a second-stage competition 1.
Kenya's procurement Act defines a framework agreement as an agreement with selected suppliers or contractors for a definite term, for goods, works or services whose quantities and delivery schedules cannot be fixed at the outset 4. A framework contract under the same Act carries a commitment to order a minimum quantity 4.
When buyers can use them
Article 32 of the Model Law allows the procedure where the need is expected to arise on an indefinite or repeated basis, or may arise urgently during a given period 1. The procuring entity must record its reasons and the type of agreement chosen 1.
Kenya's 2020 Regulations allow framework agreements where quantities and delivery schedules cannot be fixed in advance and the need recurs over a set period, under regulation 101(1) 3. Tanzania's 2023 Act uses the same two tests as the Model Law, a recurring need or an urgent need, in section 52(1) 1,5. Uganda's Act describes a framework contract as a schedule of rates or an indefinite delivery contract, used for needs on call or to cut costs or lead times for repeated needs 6.
How long they last
Term limits differ between rule sets 1,23.
| Rule set | Maximum term | Other limits |
|---|---|---|
| EU Directive 2014/24/EU 2 | Four years, longer only in exceptional cases duly justified, recital 62 2 | Only authorities identified in the agreement may use it, recital 60 2 |
| Kenya Regulations 2020 3 | Three years, regulation 102(1)(c) 3 | At least seven alternative vendors, regulation 102(1)(b) 3 |
| UNCITRAL Model Law 1 | No fixed term in the provisions reviewed 1 | Value estimated as the maximum total over the entire duration, article 12(2) 1 |
Placing orders
Under EU recital 61, where an agreement with several operators sets out all terms, the buyer may award a specific order to one operator chosen by objective criteria or hold a mini-competition among the parties 2. The procurement documents must state the criteria that decide which route applies 2. The recital says framework agreements should not be used improperly or in a way that prevents, restricts or distorts competition 2.
Kenya's regulations 101 to 106 cover tender requirements, call-offs, mini-competitions, price indexing and ordering 3. Under the Model Law, a framework agreement procedure without second-stage competition is exempt from the standstill notice in article 22(2), under article 22(3)(a) 1. The entity must publish notice of the award under article 23(1) 1.
Rules in other countries and lenders
- Tanzania: section 52(2) gives the Government Procurement Services Agency, with the Authority, the role of setting procedures for common-use items bought through framework agreements 5.
- Uganda: section 60(2)(b) tells entities to make use of framework contracts wherever appropriate 6.
- Malawi: section 54 of the 2025 Act permits framework agreements as set out in regulations 7.
- Zambia: section 2 of the 2020 Act defines a framework agreement as an agreement with a selected supplier or contractor for a definite term, and section 57(1)(b) encourages rate or running contracts for recurring needs 8.
- South Africa: the 2024 Act defines a transversal term contract as one arranged by the relevant treasury or another procuring institution mandated by legislation 9.
- World Bank: the September 2025 Procurement Regulations list framework agreements among contract types and arrangements in paragraph 5.27, with details in Annex VIII 10.
Common questions
What is the difference between a closed and an open framework agreement?
A closed agreement admits no new suppliers after it is concluded. An open agreement allows suppliers to be added later 1.
How long can a framework agreement last in Kenya?
Up to three years, under regulation 102(1)(c) of the 2020 Regulations 3.
Can an EU framework agreement run longer than four years?
Only in exceptional cases that are duly justified, according to recital 62 of Directive 2014/24/EU 2.
How are orders placed under a framework agreement?
Suppliers are selected in a first stage. Orders then go to a party chosen by objective criteria or through a second-stage competition among the parties 1,2.
Rules and fees change. Check the official site linked above before you apply or pay. Spotted an error? Email [email protected] with the official link.
Sources
- UNCITRAL: Model Law on Public Procurement (2011)
- EUR-Lex: Directive 2014/24/EU of the European Parliament and of the Council on public procurement (26 February 2014)
- Kenya Law: Public Procurement and Asset Disposal Regulations 2020, Legal Notice 69 (30 April 2020)
- Kenya Law: Public Procurement and Asset Disposal Act 2015, revised (31 December 2022)
- PPRA Tanzania: The Public Procurement Act 2023, English translation (20 September 2024)
- PPDA Uganda: Public Procurement and Disposal of Public Assets Act, Cap. 205 (accessed 20 October 2026)
- Public Procurement and Disposal of Assets Authority Malawi: Public Procurement and Disposal of Public Assets Act No. 7 of 2025 (31 January 2025)
- ZambiaLII: Public Procurement Act 2020, consolidated with Act No. 17 of 2023 (26 December 2023)
- Government Gazette No. 50967: South Africa Public Procurement Act No. 28 of 2024, copy hosted by ddyn.com (23 July 2024)
- World Bank: Procurement Regulations for IPF Borrowers, Seventh Edition (September 2025)
Related
- Open tendering explained
What open competitive tendering is, the steps from notice to award, and the rules in the UNCITRAL Model Law and World Bank Procurement Regulations.
- Single-source procurement explained
What direct or single-source procurement is, when the UNCITRAL Model Law and World Bank rules allow it, and how Kenya, South Sudan and Uganda apply it.
- Public procurement in Kenya
Kenya's procurement law, methods, direct procurement rules under section 103, the Review Board, and privately initiated PPP proposals.
- Public procurement in Tanzania
Tanzania's Public Procurement Act 2023, PPRA, procurement methods, direct and single source rules, PPP unsolicited proposals and appeals to the PPAA.
- Public procurement in Uganda
Uganda's PPDA Act as amended, the PPDA Authority, procurement methods, direct procurement conditions and appeals to the PPDA Appeals Tribunal.
- Public procurement in Malawi
Malawi's PPDA Act 2017 and its 2025 replacement, the PPDA, open tender and single sourcing rules, where thresholds are set, MANePS and reviews.
- Public procurement in Zambia
Zambia's Public Procurement Act 2020, the ZPPA, procurement methods, direct bidding rules, where thresholds are set, e-GP and appeals.